Gate 304, built for the rush
The alco test is in the lane, the whole gate arrives in one container, and every decision stays at the gate.
- ~7 sface and alco test in the lane
- 3 lanesin for the rush
- 1container, built off site
- Wk 6first lane live
Targets for the pilot to measure. Nothing on this page is measured yet.
The gate, one shift at real pace
The Olefins Plant gate at Long Son, on onoto.ai's 3D engine. Switch to Plan to follow one worker through each edge case.
Same shift change, two designs
Same buses. The draft tests at two stations before the lanes. Ours tests inside the lane, with lane 3 turned to entry for the rush.
Simulated. Buses of 40, walk-ins between, 1 in 80 tests positive. The 7 s lane test is the vendors’ claimed time plus the walk through, not measured: drag it to 15 s for a slow unit. Orange dots have waited over 5 minutes.
The gate decides. The cloud runs every gate.
Every pass is settled at Gate 304 with any link cut. ONOTO Cloud ships the updates, the models and the dashboards.
- Decides a pass, at the gate
- Sync inside the plant
- Outbound to ONOTO Cloud
- Phase 2
- Click a box for what it needs, sends and connects to
What we build
We buy the hardware. Everything that decides, learns or reports is ours.
Bought, not builtFace + alco lane unitsTurnstilesContainer gate shellCamerasHandheld evidential testerSmall GPU boxPoE switchesNVR and UPSAll fitted and tested in the container before it ships
How the data moves
Every link, what crosses it and how often.
| From → to | What crosses | How | When |
|---|
What changes from the draft
| Area | LSP draft | Our design |
|---|
Live during the turnaround
One lane in shadow mode by week 6, so the turnaround crowd is the test.
Graded byGuard spot checksVideo reviewEvery week, not the system's own dashboard